R M SCHAEFFER PIPING REDIRECT

Wheatfield, Indiana

Wellpoint installation for 30-inch pipeline and deep wells for large open-cut excavations. 

THE CHALLENGE

Numerous excavations requiring dewatering systems that varied from 30 ft. jetted deep wells to jetted wellpoint systems. Wells could not be installed by drilling due to the high water table.

THE SOLUTION

Installation by jetting with the Griffin Track Punch Jetting Tool for both the deep wells and wellpoints alleviated the challenges typically associated with installing wells in an area with a high water table.

GRIFFIN DIFFERENCE

Griffin had prior experience at the project site and knew what it would take to get the job done. Flexibility with installation techniques provided the most cost-effective solution.