  • FILLMORE PLAZA CONSTRUCTION

    Project Location: Denver, CO Owner: Confidential GC: Saunders Construction Project Revenue:  $372,000.00 Project Timeline: August 2016 – February 2017 The Challenge: The excavation for the deep foundation extended through sand and gravel alluvium near Cherry Creek and into claystone bedrock in the deepest sections. Specialized drilling equipment is required when dewatering excavations near an impermeable material such as…